Member
2010-11-30, 08:10 PM
I've gone through the forums on this, but is there a way to keep projects which do not have available actions from showing in a perspective? A way other than setting a start date for the projects?
Right now, I have five projects filled with actions which have starting dates set for the next few days -- a few tomorrow, others at the end of the week -- but with the Availablity Filter set to available the projects are showing up as available despite being un-actionable.
To put it in programming terms: shouldn't a parent object (a Project) be affected by the action status of it's child object (an Action) so if there are no available child objects, the parent will also hide?