Thanks for the tip whpalmer4. I am attaching the 'scrambled' version of the omniplan project that I have been working on.

The problem is occurring within 'Resource 2'. The tasks that are receiving the priority are: Tasks 16, 22, 28, 34, 40, 46, 52, 58, 65, etc (Green tasks). The tasks that should be getting split and filling in the remaining areas are: Tasks 277, 283, 289, 295, etc (Blue Tasks). I am sure that the same thing is happening throughout all these tasks so we could probably just focus in on Tasks: 22/28 & Task 277.

Please let me know if I should include anything else. (I am also sending the e-mail to the support ninjas through the 'Send Feedback' menu).
Attached Files
File Type: zip Jarrod-12-02-13-1.oplx.zip (47.8 KB, 566 views)