I've got this scenario: I have a milestone called Project Finished which moves around based on its dependencies. I'd like to have a QA task that has a fixed duration (6w) that needs to start as late as possible, finishing at the same time as my Project Finished. Is this possible? I've only been able to adjust this task manually, moving it forward as the Project Finished milestone moves forward.

thanks
Collin