Hi All,

I'm hoping there's an easy solution to this:

My organisation uses a 7.5 hour working day, so I've changed both the Normal Working Week and the Project: Unit Conversions data from the default 8 hour working day to use 7.5 hours.

However when I enter a task, its default duration is 1 day 0.5 hours, e.g. it is still using the default 8 hour working day settings.

Can this be adjusted? Any tips appreciated!

Cheers,
Alex