Hi all,

I imported a template file from MS Project which I purchased on the internet so I cannot change the original MPP file. Everything works well except that the project shows a length of 573 weeks but is actually only 108 weeks. For some reason the first task starts at T+465 and everything moves up from there. Is there a way to reset this to start at T+0 so that all the subsequent tasks are corrected in sequence or will I have to reset each one in the task inspector individually?