Originally Posted by whpalmer4 View Post
Why don't you want to view Projects showing Remaining instead of Available?
I am showing Remaining in the Projects view. But here's the problem. I have a hierarchy set up, say:

Project X
Construction
Coding
Permits
Set up Y
Offices
Set up Z
Research
ABC
Testing
Demo
"Set up Y", "Set up Z" and "ABC" are all black (indicating available to do). Everything else is gray.

So looking at my project it appears that Construction (for instance) isn't ready to be worked on yet even though it very much is, as I have to set up Y & Z and do research into ABC.

And looking at these tasks in Context view can be confusing. What if I have TWO "Set up Y" tasks, but under different parents? And one is due today and the other a week from now? How do I know which one to work on today when the only visible differentiator in this view is the Project Name and they're both the same?

I could swear it didn't used to be this way... Or was it?