Well, I was just disappointed to find that a sequential project with a due date attached to a later action does NOT make the preceding actions due, too. That is, given this:

Project: apply for grant (seq)
- pick up forms @errands (no due date)
- fill out forms @work (no due date)
- turn in forms @errands (due 10/1)

If I viewed my available actions by due date, "pick up forms" would show up as having "None." This is technically correct, but means that the actual urgency of this project won't show up in context view until the last action is up, which may be too late!