Originally Posted by cyork View Post
I have tried both these options and can only add project date to the first task. Please advise.
Once you set the project start date to undetermined, you can select a task, bring up the Task : Information inspector, then type "T + 10 days" in the actual start field. Now, that task should start 10 days after the project start date.