Originally Posted by mprewitt
I've got 15 tasks in the project, with three staff resources handling those jobs over a period of months. Splitting those three staff into multiple staff resources as a workaround would throw off the entire timeline. Especially since some tasks require a staff resource's full time.
While it might be considered a workaround, I've been setting the Assigned Amount for a resource assigned to a task to the level-of-effort being applied to the project by that resource.

So, if I want to commit a resource to "1 hour per day" on a particular task, I assign 12% (of an 8-hour day [approx]) of the resource to that task.

From my preliminary testing, that appears to level as I would expect.

YMMV.