View Single Post
Did anyone find a solution to the OP's problem? I have the same issue. I have an underway project. I have been advised someone discovered an issue and started a previously unknown task 3 days ago (21 May). Dependent tasks (testing etc) now need to get connected to it. I can't for the life of me get the task into my plan with a start date of 21st. OmniPlan insists the start day is today and trying to move it backwards simply creates a constraint that I don't want. Why can't I modify the plan for prior dates?