How can I get OmniPlan to stop using the time-of-day in its schedules? I know that I can make it not display the time of day, but it still uses it. For some crazy reason when I re-level things, it will move stuff around that used to start at 8:00AM on a Monday to suddenly start at 10:45AM on a Tuesday, or something crazy like that.

Again, this is tied to another issue I am having with leveling and its interaction with percentage-complete values.

Regardless of why, I do not want a tool that seriously thinks I want a five week project that starts at 2:17PM on any particular day. Nothing I plan has that level of granularity. If I can hide the time from displaying, why can't I stop it from being used in calculations?