Thread: Counting weeks
View Single Post
Quote:
Originally Posted by juliabell View Post
I have a task with a start date of June 7 2010 (task 3.4.1.1) (Monday).
I created a milestone with a constraint of 3.4.1.1SS+2w.
The milestone date is June 18 2010 (Friday).

I expected the milestone date to be June 21 (two full weeks after the start of the task).

Why is the milestone scheduled only 7 working days after the start of the task?
Aaron has told you why the milestone is when it is, but I'm curious about this "only 7 working days" bit -- is that just a mistake in your counting? If the task has a start date of Monday Jun 7, how would Friday Jun 18 be only 7 working days later if you are working 40 hour weeks, 8 hour days with no intervening holidays or vacations?