I am having a problem with iCal sync in OmniPlan 2.0.2 that is driving my crazy.

I have my project laid out. A really important workflow for me is to have my project time laid out in iCal, populated by those tasks in OmniPlan that span across that Working Time - and we're very nearly there, but it doesn't seem to be quite right.

I am using "Sync tasks to/from iCal events" to do this and it largely works. The problem I have is that I only want the Working Hours for me as a Resource occupied by blocks in iCal. Again, this works fine, except for one when one task starts mid-way through one Working Hours block and its duration takes it beyond into the next block in iCal. When this happens, unfortunately the iCal appointment stretches all the way to the next Working Hour block, bulldozing its way through the rest of my calendar appointments.

Rather than sync to iCal, if I export the project to iCalendar I at least get the "One per work period" keeps my OmniPlan stuff only within the Working Hours I have set as a Resource. Why doesn't this happen in syncing?

Any help would be much appreciated. Thanks.