The very last item in my plan is scheduled As Late As Possible and has an end constraint. All other things being equal I would expect it to be scheduled so it finishes at it's end constraint time.

Yet when I level the resources it gets rescheduled to several days earlier than it's end constraint for some reason I can't fathom.

However if I add an unrelated milestone to the project at some point in the future beyond the end constraint time above and level, my task is rescheduled to end at it's end constraint time - as I would expect.

This only occurs to the task that is furthest in the future in my project.

Have I misunderstood something?

(Using V2.0.3)