OK - quicker example.

Create a new project with one task.

Set an end constraint on that task of several days into the future, schedule it As Late As Possible and level.

It seems to stay where it is, as if it were scheduled As Soon As Possible.

Add a second task beyond the first and level.

The first task moves to finish on it's end constraint time.

Remove the second task and level.

The first tasks shifts back.

Is this correct?

Last edited by psidnell; 2012-04-27 at 11:29 AM..