Originally Posted by davisre View Post
OmniFocus makes a distinction between "next" actions and "available" actions. In a sequential project, there's no difference, but in a parallel project, all of the actions become available while there remains just one next action.

This way, people adhering to strict GTD can filter for next actions and see at most one per project, but others can filter for available actions to see everything that can now be done, taking into account the parallel-vs-sequential setting on a project or action group.
I understand all that. But in addition to parallel and sequential projects there is the Single Action List and *All* items in the list are next actions. There is one that comes standard called "Miscellaneous".

But when I create a new Single Action list and try to move it to my project it transforms to a parallel project and now only shows the first item as a next action.