View Single Post
I'm trying to re-position some tasks in time and OmniPlan will not let me. When I drag the task earlier in time the constraint time gets set earlier but the task itself moves back to where it started in time.

There are no locked start and end times, no dependencies, and no connections.

There are two overlapping groups each with their own tasks that seem to be somehow dependent in a way I cannot figure out. Is there some way that overlapping groups (and their respective tasks) interact that I am not seeing?

Any suggestions?