I have several finish start dependencies where the second task must be finished 30, 60 or more days after the first.

For example, I need task B to be scheduled 30 days after task A is finished. I do not want to put a hard date in the constraint for task B because the finish date for A may change. I would like the schedule for B to automatically reflect the 30 days from the date that A is actually finished.

How can I do this?
Once you connect task A to task B with a finish to start dependency, make sure task A is selected and bring up the "Task : Dependencies" inspector. You should see a column named "Lead Time". Click in that field and type in your lead time of 30 days and that should do it.