View Single Post
Quote:
Originally Posted by whpalmer4 View Post
What are the due dates on those subsequently created tasks? It only populates the next 14 days, so if your due dates fall outside of that range, it will appear not to work.

If that isn't the issue, you should contact the support ninjas via Help->Send Feedback or phoning 800-315-OMNI or +1-206-523-4152.
Yep that answered my question. All my subsequent due dates are at least 14 days later. Just tested again with due dates with in 14 days and they all showed up.

Why is it designed that way? Is there any way to change that? My job requires me to plan way beyond 14 days and I need to see the due dates for my tasks so that i know when to or not to book a meeting.

btw thanks guys for helping. :)

Last edited by Randomplay; 2011-03-16 at 11:29 PM..