Originally Posted by lazyline77 View Post
the items listed within "Due within the next week" are incomplete. It is only showing actions from within one of my "Single-Action Lists". Why would Omnifocus prioritize those actions for the "Due" view?
Quote:
Originally Posted by whpalmer4 View Post
My guess is that you have entered these as sequential projects, and are viewing Available actions.
In OF 1.8, using Where in OF, you could quickly check which projects are set as sequential by running the saveable search:
projects where sequential is true
Tasks flagged as sequential inside generally parallel projects could be listed with:
tasks where sequential is true and (sequential of its containing project is false)
and a simple listing of tasks due within the coming days could be generated by some variant of:
tasks where (due date ≥ today) and (due date ≤ (today + 6 * days))
--