Just put in milestones for these assorted dates, with start and end constraints on the milestones to keep them in place on the desired dates. Each phase of work will end with a finish-start dependency to the milestone signifying that it has been completed. If you've constructed your project correctly, using dependencies and lead times to express the interrelationships between various actions, and *NOT* just specifying dates for all the tasks, you'll get violations if your proposed plan doesn't meet the requirements.