I've been fiddling around with the effort and duration settings in the resource assignment info tab.

As you probably know, the default is "Keep Effort Fixed". However, for our environment and planning process, I've come to the conclusion that the setting of "Keep Effort and Duration Fixed" is most useful.

Is there any way of specifying "Keep Effort and Duration Fixed" as the default setting so we don't have to go into every new task to set it so?