I've not read the Gant book so I might have missed out on the basics, but

Can't I have a Task with a higher "task no" make a Finish->Start dependency for a task above?

I've tried connecting the two with all Types of connections, then click on "Level". But tasks underneath doesn't seem to push the ones above further in time.


thanks
david