View Single Post
Quote:
Originally Posted by iNik View Post
In the preferences there's an option for default review dates and whether they're "fixed" or "unfixed." What's the difference?

Also those settings are marked as the default review interval, but there's no option in the inspector to change from fixed to unfixed for a given project. I suspect the un/fixed setting is global, in which case it should probably be reorganized in the preferences.
My guess is that fixed is the same as "from assigned date" in repeating actions: that is, if I say a review should be done every week, the next review date is Friday 9/21, and I don't do the review until Sunday 9/23, "Mark Reviewed" will set the next review to Friday 9/28, not Sunday 9/30. I put in a feature request for that a week or two ago.

However, on testing, that doesn't seem to be the case--at least not with old projects. Anyone else have an idea?