View Single Post
Thank you for the reply.

I have been trying to find a pattern, and don't really have a specific clue.

I created 12 projects under a 'Tickler' folder (in Planning mode), each named for a month, each with a review date 15 days before the beginning of the month, and each with a review interval of 1 year.

I then can create a new project under a specific month, and when I do a review, that specific month's Tickler project will show up 15 days before the month in question.

Please take a look at this screenshot, with three created actions under the 'June' Tickler project. I used different dates for start and due dates.

http://forums.omnigroup.com/attachme...1&d=1240460371

Now, if I grab Tickler Action 4 and drag it to the 'Mac' context, it disappears from this view and i can find it in the 'Mac' context. The view does not change.

But if I grab the Tickler action 5 and drag it to the 'Mac' context, I get the new view (still labeled 'Perspective:Tickler' on the toolbar, but with no context highlighted in the sidebar):

http://forums.omnigroup.com/attachme...1&d=1240461099

(Note that I have dragged the window so you can see where the dragged action is found).

Does this have to do with Active vs Blocked actions? With the dates?

I would like to be able to work out of the Tickler perspective and drag a bunch of actions into the appropriate contexts without jumping back and forth between different contexts.

Thanks for the help!
Attached Thumbnails
Click image for larger version

Name:	Picture 2.jpg
Views:	696
Size:	19.2 KB
ID:	906   Click image for larger version

Name:	Picture 4.jpg
Views:	719
Size:	19.8 KB
ID:	908  

Last edited by sawxray; 2009-04-22 at 08:30 PM..