Hi,

How would be the procedure for adding external deliverables do a chart.

If I'm waiting for electronic parts etc, I want tasks dependent to those leveled after est. delivery dates.

External deliverables from for example external graphics people. I don't want to plan them as a Task with Time (start/end), I just want to insert a date where I expect to receive the graphics.

I might have missed out on the whole Resource -> Material type. ? any tips!?