Lizard and JKT,

Thanks for the clarification.

In terms of issues, I am unable to import from OmniOutliner. I tried doing this via TSV and direct import\open. When I try the latter, the pop-up is displayed with the field matching and all looks good but when the tasks import into OmniPlan, all of the tasks have erroneous data. For example, I have about 110 line items in OmniOutliner with a variety of information in the "Task" field and after import, all the tasks have "Task" for the Task Name rather than the actual content s as in OmniOutliner.

Am I doing something wrong?