I cannot find the Applescript. If the link changed, would you please post it again?

Thank you.
This script is no longer required. Now, you can simply select all the tasks in one project plan and copy/paste it into another project plan to merge the two. As long as you have named all of your resources identically in both projects (Bob in project 1 and project 2, not Bob in project 1 and Bobby in project 2) you won't accidentally double-up on resources after the merge.