In my project, I'm not worried about hours, or the fact that a day might have 8 hours of work in it. I'm planning it out at the level of total days for contractors that don't work by the hour - so if I think this task should be done in 1 week, that's 7 calendar days total. But in OmniPlan, when I type "7d" into the Effort for a task, it automatically changes it to "1w 2d". How can I make it stop this?

Mike