View Single Post
Quote:
Originally Posted by akwong View Post
You can select the task, bring up the "Task : Assignment" inspector, and change the percentage to 50% of 100%. Do this for the other task and you'll be smooth sailing. :-)
Great, now, is there some support for more complicated operations? I have the same issues but I want to say, "Both occur over this period and end at the same time." i.e. simultaneously. But, one task takes 25w and another takes 4w. Sure, I can manually calculate the percent but is there an automated way?

i.e. 25/29 ~= 86% and 4/29 ~= 14%

Or, is there a way to say, "50% of your time on X and the rest on the remaining projects?"

Last edited by cwingrav; 2009-03-06 at 08:01 AM..