Originally Posted by cvandyck
I've got this scenario: I have a milestone called Project Finished which moves around based on its dependencies. I'd like to have a QA task that has a fixed duration (6w) that needs to start as late as possible, finishing at the same time as my Project Finished. Is this possible? I've only been able to adjust this task manually, moving it forward as the Project Finished milestone moves forward.

thanks
Collin
Scheduling a task/milestone to start "as late as possible" is a feature request in our database. I will add a vote to it for you.

A finish to finish dependency between the QA task and the milestone work allow you to tie the end of the QA task to the milestone. If you create this dependency, make sure you reset both the milestone and QA task's schedule in the "Task : Information" inspector so that it starts "as early as constraints allow".