No, Craig, the big problem with "available" is that OF defines Actions without any start date as "available". I have hundreds of Actions without start dates. I don't want to be forced to allocate start dates to get around a problem that could be so easily fixed. If there was an on/off check box in Preferences that enabled a user to define "available" as only those Actions with Start dates, then your suggestion could get around the problem, but "available" is also affected by whether a Project is Parallel or Sequential or Singles. I think it should be a Perspectives option.

Last edited by watchit; 2010-06-09 at 01:26 PM..