Does this mean we can't mark certain days as 'holidays' or 'non-workdays'?

One of my clients is closed on Fridays during the summer months. I'd like to be able to block off these days as 'closed'/'holidays'/'non-workdays'.


James B
The procedure I described will work for both general patterns -- the shop is closed every Monday -- or specific variations -- I'm on vacation next Friday.

For general patterns that affect the whole project, use the "Normal Work Week for Project". If it just affects one resource or group of resources, use "Normal Work Week" for the specific resource. If it's a specific variation, use the "Work Schedule" for the relevant scope (project or resource) and select the week to edit.

If you've got more specific questions on this, it may be easier to email omniplan@omnigroup.com