Here is one approach to exporting from Merlin to OmniFocus in a way that translates resources assigned to Merlin activities into the contexts assigned to OmniFocus tasks.

A Merlin activity may have several resources assigned to it, whereas an OF task has only one context.

The approach adopted here is to deal with activities that have multiple 'assigned resources' by giving their corresponding tasks, in OmniFocus, a set of resource-specific sub-tasks, each of which has a different context.
This is even better than your first scripts and a really good help in setting your review agenda for projects using OFs forecast once activities are imported, thanks a lot.

I wonder, though, is there a way for the script to identify resources as contexts when they already exist in Omnifocus under a context group? I group mine under "Contact" and "Waiting for" simply to avoid a long context list. Contexts at top level are recognised by the script, but once "hidden" under a group they are not.