Quote:
Originally Posted by pslade View Post
I agree it would be good to be able to change the resource availability after it has been assigned. It would be even better if you could specify the availability for a date range. I have situations where I know someone is only available for 3 weeks at 60%, but then will return to 80% afterwards
Have you thought about modifying that person's work schedule to reflect their (presumably) reduced hours during those three weeks?