Our people work 21 days and 21 days they are off work. They get paid 7 days per week 12 hour per day.
I have set the work schedule Monday - Sunday 6 AM - 6 PM.
This has not changed in the Project Formatting the working hours / day / week / moth / year /
In the Resource Information the working hours remain 8h instead of 12h
It also calculates with 8h.
What have I done wrong ? Please help