Hi,
Just a quick question:
Is there an easy way to delay all tasks in a project by a day (or whatever)?
Due to unforeseen circumstances I occasionally need to delay a project with several tasks in it by a day or two? But I have been changing each task manually by a day which is quite tedious (especially when there are many tasks).
sorry if this has been covered (I had a brief search through the forum but couldn't find an answer).
Cheers
Just a quick question:
Is there an easy way to delay all tasks in a project by a day (or whatever)?
Due to unforeseen circumstances I occasionally need to delay a project with several tasks in it by a day or two? But I have been changing each task manually by a day which is quite tedious (especially when there are many tasks).
sorry if this has been covered (I had a brief search through the forum but couldn't find an answer).
Cheers