Visualise milestone risk without moving baseline? Thread Tools Search this Thread Display Modes
Hi All,

I have a current project which I'm tracking with OmniPlan and until now, all has been tickety-boo. Unfortunately, some bright spark threw a "spanner in the works" which places the various milestones in serious jeopardy.

Is there a way to keep the baseline planning static and visible, but show a projected impact of the risk at the same time. I am okay with it throwing up dependency violations as a result of the slow or stalled progress of certain tasks/dependencies, but want to keep visualisation of the PLANNED milestone, as well as the forecast milestone projected out as a result of the stalled process. Currently, if a task changes completion date, all it does is move the visible milestone without a comparative risk visualisation. In this context, there is a worry that because the milestone has changed, it may engender a sense of complacency ("oh we still have time before we need to finish this...") rather than a sense of urgency for the resources to "catch up" on the tasks required.

I have tried normalising the baseline and then making modifications to the actual, but it still doesn't really visualise the impact or risk... just moves the end-backstop date out.

I guess in essence what I'm looking for is visualising the planned progress as well as the actual progress in comparison so that we can see at a glance what risk the current progress is incurring.

Hope that makes sense...

Thanks in advance.

L.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Data risk with the OF2 private beta? wlow OmniFocus 1 for Mac 2 2013-03-19 12:49 PM
How to mark a milestone as complete? masoric OmniPlan for iPad 1 2012-07-03 08:47 AM
Waiting for Milestone...? gersaky OmniPlan General 7 2009-09-25 10:36 AM
Milestone Formatting? lally OmniPlan General 1 2006-11-06 05:13 PM


All times are GMT -8. The time now is 01:54 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.