7.5hr day still results in 8hr default tasks Thread Tools Search this Thread Display Modes
Hi All,

I'm hoping there's an easy solution to this:

My organisation uses a 7.5 hour working day, so I've changed both the Normal Working Week and the Project: Unit Conversions data from the default 8 hour working day to use 7.5 hours.

However when I enter a task, its default duration is 1 day 0.5 hours, e.g. it is still using the default 8 hour working day settings.

Can this be adjusted? Any tips appreciated!

Cheers,
Alex
  Reply With Quote
Create a task that is in all ways how you want your newly created tasks to be*— background color, duration, effort, etc. Select Project->Set as Default for New Tasks and all tasks you subsequently create for the project will use that as a template. (Note however that if you change your "template" the existing tasks will not update, OmniPlan just takes a snapshot of what your task looked like at the time you issued the command).
  Reply With Quote
Ah! Simple :)

Thanks for the tip, much appreciated.

Cheers,
Alex
  Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Repeating projects and default tasks? nielsk OmniFocus 1 for Mac 4 2010-12-31 01:00 PM
Repeating tasks and default time Sandpiper OmniFocus 1 for Mac 7 2008-08-20 11:14 AM
Feature request - default insert location for new tasks dondo OmniFocus 1 for Mac 0 2008-07-21 10:32 AM
OmniFocus: Querying tasks in Applescript gives odd results RobTrew AppleScripting Omni Apps 0 2008-03-01 01:03 AM


All times are GMT -8. The time now is 04:24 AM.


Powered by vBulletin® Version 3.8.6
Copyright ©2000 - 2013, Jelsoft Enterprises Ltd.