Most of the tasks in my project are created from AIs (Action Items) assigned during meetings.
I want to quickly enter these tasks in OP assigning them just an end date, but I do not want to have their types be 'milestone', since they are not milestones by my definition and would limit filtering later on.

What is the best way to do this ?
i.e. If the 'Type' is a 'task' I am required to provide a start date or effort/duration.
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Can't change date for task started before today? [A: Remove constraint in Task:Schedule inspector] chaloum OmniPlan General 11 2013-07-05 12:23 PM
Enter any Date? xtin OmniPlan General 3 2013-04-08 11:10 PM
Auto-enter date in date column richbreen OmniOutliner 3 for Mac 4 2012-09-26 07:22 AM
Shift + Return to enter task above current SpiralOcean OmniFocus 1 for Mac 0 2007-07-08 12:36 PM
How to enter all aspects of a task using only the keyboard Elliot Shank OmniFocus 1 for Mac 1 2007-05-16 09:21 AM


All times are GMT -8. The time now is 05:06 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.