Just started using Omniplan (yesterday).....
1. Can leveling be set to be automatic? Right now everytime I add some tasks I have to level the resources again.
2. Can I set the format so that on the GANTT chart milestones don't show up with the time... looks sorta silly that this milestone will be 3/17/07 14:25
Thanks /lss
1. Can leveling be set to be automatic? Right now everytime I add some tasks I have to level the resources again.
2. Can I set the format so that on the GANTT chart milestones don't show up with the time... looks sorta silly that this milestone will be 3/17/07 14:25