The Omni Group

Go Back   The Omni Group Forums > OmniPlan > OmniPlan General
Register FAQ Members List Calendar Search Today's Posts Mark Forums Read

 
Understanding task duration Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
I've rescheduled to 'now', and leveled all of the following tasks prior to noting their effort and duration. All are at 0% completion. None are split.

I have a task that I am assigned to 100%, .25h effort, and when I add another resource (person) to it 100%, the duration remains at .25h. If I create a new task (same resource allocations; and it appears in close proximity to the previous task), 0.224h. (Or 1 hour effort becomes 0.599h duration).

I realize a variety of factors as listed in the help can alter duration; I just wanted to make sure the numbers I've listed are potentially legitimate. Thanks.

Bob
  Reply With Quote
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Separating task effort from duration doc411 OmniPlan for iPad 2 2012-06-15 03:56 PM
Adding multiple resources to a task without changing duration blaketime OmniPlan General 5 2011-10-04 11:57 AM
default task to fixed duration & default delete behavior? marya OmniPlan General 0 2010-12-27 02:23 PM
Effort vs. duration vs. period of a task vs. workload Woje OmniPlan General 2 2008-03-20 08:38 PM
Help Understanding Dates Lenmonster OmniFocus 1 for Mac 4 2007-09-17 06:00 AM


All times are GMT -8. The time now is 05:28 AM.


Powered by vBulletin® Version 3.8.6
Copyright ©2000 - 2013, Jelsoft Enterprises Ltd.