Can't change date for task started before today? [A: Remove constraint in Task:Schedule inspector] Thread Tools Search this Thread Display Modes
I have found that you also need to remove the constraint from all parent Group tasks for this to work. That wasn't obvious to me when I was working on this problem.
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
New task without any schedule Maxi OmniPlan General 0 2011-04-15 06:06 AM
Define constraint as a function of another task? juliabell OmniPlan General 1 2009-09-12 09:30 PM
How to see only task groups that have started? [A: See thread.] jaydcowan OmniFocus 1 for Mac 2 2009-08-06 07:17 PM
Daily task not done today, how do I remove it... iangall OmniFocus 1 for Mac 7 2008-12-03 03:18 AM
Dependency/constraint: End before task tlester OmniPlan General 1 2008-09-05 01:34 PM


All times are GMT -8. The time now is 07:59 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.