Gray italics means that the task cannot start yet (i.e. the start date is in the future). If you select "Available" or "Next Actions" as task filter, these items will not be shown until the start date and time.
These forums are now read-only. Please visit our new forums to participate in discussion. A new account will be required to post in the new forums. For more info on the switch, see this post. Thank you!
|
|
FAQ | Members List | Calendar | Today's Posts | Search |
a help request to the community | Thread Tools | Search this Thread | Display Modes |
|
Gray italics means that the task cannot start yet (i.e. the start date is in the future). If you select "Available" or "Next Actions" as task filter, these items will not be shown until the start date and time.
Post 1
|
Member
2007-12-02, 06:59 PM
thanks for the help.
as i said, there are no start dates for these actions, and i am viewing "Next Actions". i am confused as to why they're still in that state . . .
Post 2
|
Ten days later...did you resolve this? Did you put a start date in the future on the single-action container that the actions were in? Actions inherit the start date of their project, unless you specify otherwise explicitly.
Post 3
|
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
OmniFocus URL Support -- Community Feedback | xmas | OmniFocus 1 for Mac | 33 | 2009-11-24 06:26 AM |
Thank You OmniFocus Community! | steve | OmniFocus 1 for Mac | 1 | 2007-09-01 07:44 AM |