Hi there

If you set the baseline in Omniplan and then later on in the project have to add in new tasks, that new task should not in iteself have a baseline, as you ar adding it in to the project. As a user you want to see what change impact has been caused to the project which the baseline shows, but also what caused the change. So some different visual needs to be reperesented on new tasks added to a set baseline.

I realise this is possibly a feature request, but in my mind this is a bug, as a baseline should be ass the project was originally planned.

Thanks

chat-noir
  Reply With Quote
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
New task just with baseline schedule Maxi OmniPlan General 1 2011-05-31 04:18 AM
baseline and leading willb OmniGraffle General 0 2007-06-15 08:18 AM
Baseline and undertermined date Manticore OmniPlan General 1 2006-09-05 11:09 AM
Set baseline by mistake edasque OmniPlan General 5 2006-08-02 11:43 PM


All times are GMT -8. The time now is 10:29 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2013, vBulletin Solutions, Inc.