Hi there

How can i fix a resource so that it doesn't start until a certain date in the project (I speak of the human kind)?

I have a task breakdown for these people, but it's not reflecting accurately because I can not fix the date they are dues to start which is a few months ahead.

Thanks

chat-noir
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Start date, Forecast Workarounds for missed start dates rdbot Applying OmniFocus 8 2013-04-04 12:56 PM
Making Start Date, Due Date, Estimate Default jessicatmt OmniFocus 1 for Mac 1 2012-08-06 01:23 PM
Adding Resource Changed End Date workinprogress OmniPlan General 4 2009-10-04 12:51 PM
Problem with repeat when start date and due date exist SpiralOcean OmniFocus 1 for Mac 2 2008-09-05 04:43 AM
Sorting Columns by start date/end date/cost ..etc mr_projects OmniPlan General 5 2008-05-19 03:03 PM


All times are GMT -8. The time now is 03:57 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.