Durations / End date/times weirdness Thread Tools Search this Thread Display Modes
Hmm... Went through the whole manage attachment process, selecting from the computer, etc. Let me try again...

Ah, there's the problem. The "Upload" button is a separate action from the "Close this window" button. I'm a UX designer and would have done that differently. : )

Thanks in advance.
Attached Files
File Type: zip UX_Sched_101021_test.zip (35.1 KB, 323 views)
 
Attached are before and after screen shots of a task in the plan I posted last night.

OPlan_01_5days: Note task 2.3.1. Its effort is 5d according to the chart on the left and that matches with the task bar to the right.

OPlan_02_4.5days: I dragged/shortened the task bar directly, moving it to the left. It snapped to the next day line in the display. But note the effort: 4.5 days. The task bar clearly shows 4 days, that's what I dragged it to, yet I'm getting 4.5 days.

Thoughts?
Attached Thumbnails
Click image for larger version

Name:	OPlan_01_5days.png
Views:	336
Size:	57.4 KB
ID:	1650   Click image for larger version

Name:	OPlan_02_4.5days.png
Views:	355
Size:	47.2 KB
ID:	1651  
 
There was a disconnect between the work week and the number of hours per day in the project formatting panel. My work week was M-F from 8 to 5 (i.e. 9 hours per calendar day). My project formatting setting (at the bottom of the inspector) had a work day of 8 hours as an Effort Conversion Factor.

The next issue was my Work Schedule for Project -- I had entered a unique week for Thanksgiving. That week also had a disconnect between total work hours per calendar day vs. a resource's work day.

Bring all that into alignment and it works with a granularity of days.

What is weird is that I was able to enter a lot of information into my plan without the discrepancy showing up immediately. The settings were out of sync for a few days. Wonder what caused OPlan to decide to recalculate durations and effort on some but not all parts of the plan.

Hope this helps.
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Lead times before locked task e.g. ordering pre fixed delivery date marcd OmniPlan General 10 2009-09-03 06:54 PM
Perspective weirdness Chris OmniFocus 1 for Mac 1 2008-01-08 12:49 PM
remove times in start and due date creativityist OmniFocus 1 for Mac 18 2007-12-15 12:58 PM
Print as PDF weirdness jmckeown OmniWeb General 1 2007-05-22 09:45 AM
OW encoding weirdness with MT Gregory OmniWeb Bug Reports 0 2006-11-17 07:38 PM


All times are GMT -8. The time now is 05:15 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.