Is there any way group people together to config a group calendar? I am planning a project right now that has people in the US and Canada working on it. Our holidays are different. FOr example, in Canada they have July 1 off for Canada day and here in the US we have July 3 off for July 4 :)

And so on through the year. I really don't want to setup an individual calendar for each person on the team. Is there any way to partition the people for this purpose?

Thanks.
 
Never mind... I discovered GROUPS :)

/lss
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Viewing ONLY groups in Resource View jaaronfarr OmniPlan General 0 2013-01-14 12:08 AM
Resource shared in two 'resource groups' t-awesome OmniPlan General 1 2010-05-11 04:51 PM
1 resource, many groups arcticflea OmniPlan General 1 2008-04-24 10:35 AM
Showing total resource cost for task groups? docswab OmniPlan General 4 2007-01-04 05:03 PM


All times are GMT -8. The time now is 09:01 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.