Possible Bug, can someone please confirm - Effort-Duration-Change of days per day Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
Ok here is the situation.

Create an activity with a effort of 8h.
Assign it to someone with a work schedule of:Mon 9am - 3pm, and Thur 9am - 12pm.

Make sure your project hours per day is set 8h.

The durations of the activity should now be 6d 3h.

Now change your project hours of work per day to say 24h or 1h.

The duration in the WBS changing according to the Project hours per day. But the Gantt is unaffected. Start and end dates are also unaffected. BUT the Duration seems to be linked with the Project hours per day even when it should not be because of custom work schedules.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
change effort w/o changing duration juicychus OmniPlan General 2 2007-11-27 02:40 PM
Keep duration as days? starkos OmniFocus 1 for Mac 0 2007-10-22 07:34 AM
Spread effort based on duration and total effort Hap OmniPlan General 1 2007-02-14 04:50 PM
effort/duration toddbg OmniPlan General 1 2006-09-05 11:05 AM


All times are GMT -8. The time now is 09:00 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.