I am building a template. How do I key the start date of a task from the start date of the project when the start date of the project in not determined yet? In other words, if I know I want to have completed a task 10 days after the project start date, how put that into the template?
 
I answered the specific 'complete 10 days after project start' question in the other thread. But in general, if you want to plan a project without specific dates, you can switch the whole project over to generic dates.
In the Project: Information inspector, there are two Start options:
(1) Undetermined Date and (2) On [12/08/08 8:00 AM].
By default, option 2 is selected and filled in with today's date when you start a new project. Instead, you'll want to choose option (1).
 
Quote:
Originally Posted by Lizard View Post
I answered the specific 'complete 10 days after project start' question in the other thread. But in general, if you want to plan a project without specific dates, you can switch the whole project over to generic dates.
In the Project: Information inspector, there are two Start options:
(1) Undetermined Date and (2) On [12/08/08 8:00 AM].
By default, option 2 is selected and filled in with today's date when you start a new project. Instead, you'll want to choose option (1).
I have tried both these options and can only add project date to the first task. Please advise.
 
Quote:
Originally Posted by cyork View Post
I have tried both these options and can only add project date to the first task. Please advise.
Once you set the project start date to undetermined, you can select a task, bring up the Task : Information inspector, then type "T + 10 days" in the actual start field. Now, that task should start 10 days after the project start date.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Location-based tasks and start date - BUG! [A: filed as feature request.] vitvit2002 OmniFocus for iPhone 4 2012-09-04 10:25 PM
Repeating Tasks... Don't want it to show until start date. adk365 OmniFocus 1 for Mac 4 2008-12-12 10:47 AM
Why are new tasks created on the start date of the project, not today? sbwoodside OmniPlan General 11 2008-05-06 02:49 PM
Bug: single tasks with start up date in the future brab OmniFocus 1 for Mac 0 2007-06-05 01:58 AM
Bizzare Scheduling when linking Finish - Start Nedzb OmniPlan General 1 2006-12-06 03:58 PM


All times are GMT -8. The time now is 08:20 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.